Tiling installation pau!

No pictures today. They’d look pretty much like all the other pictures.

Tiling is complete and the bedroom and bath are awash in dust. Straight cuts in the tile were made with your standard score and snap tile cutter. Notch cuts were made with and edge grinder which was smaller which was less messy than a wet saw, but it generated a good amount of really fine silica dust. The cleanup process will not be quick.

My number one job today was to acquire grout. Laurel and I had found a variety at Flooring Direct Maui, a small retailer, that was just the right shade. The other vendors, including the big box stores, just didn’t seem to have what we were looking for. Paul, our tile guru, had requested 25 lbs of un-sanded for the walls and 10 lbs of sanded for the floor–grout type based on the size of the joints.

When I got to Flooring Direct, I was told they could only come up with 15 lbs. of un-sanded and no sanded. After some digging, they did find two 9 lbs. bags of sanded. I took it all. When I returned to the condo, I did a few calculations using charts on the grout bags and figured we needed someplace a little over 9 lbs. of un-sanded and little over 6 lbs. of sanded. We should be in great shape with the grout.

Just in case the grout I had wouldn’t work, I stopped by Lowe’s to see what they had. They had nothing we could use in the way of grout, but while I was there, I checked on commode that I was unable to find the day before and not only did they have one, but the price had dropped over $60. It was really the one I wanted, so I headed home, squeezed the old one into my compact Chevy, returned it to HD and bought the new. If I’m making two trips to town in one day, we must be in the middle of a 10-209 construction project.

We’re finally tiling

We’re finally at the place in the process where tile is going up. Today, it’s anticipated that the wall tile below the accent stripe will go up. If the lower sections set up enough, he may be able to go higher. A second coat of waterproofing also needs to be added to the floor.

We now have two commodes in the hall; one old, one with some assembly required.

[nggallery id=8]

Waterproofing & poopers

Today the waterproof coating was applied to areas of the wall and the pan. I’d hoped to get in there and do some paint prep and a little trim painting done, but the waterproof goop took a long, long time to dry. I didn’t want to damage it, so any paint preparation will be delayed for a day. Tomorrow, we start setting wall tile.

After a good deal of review, the decision was made to go with a 6-tile wide accent stripe. It should balance nicely with the 6″ tile size.

The big chore of the day was a trip to town to find a new commode of the comfort-height variety. Both Home Depot had Kohler models that weren’t too bad. I found it interesting that both big box stores carried the same model name, but with different UPC and the Lowe’s item was 6/10″ higher. It was also a few bucks cheaper, but when I went to buy it they could find one to sell me. The inventory database showed five on-hand, but none were to be found. I wonder how they ever turn a profit. Anyway, the toilet is in the van and I’m going to try to get Paul, our tile guy, help me get it up to the unit.

[nggallery id=7]

Putting in drypack

Early this morning, I was off to the swap meet, the “club” (Costco), Foodland and Safeway for some grinds. By the time I got back around 10:45, Paul and his helper had the rest of the wallboard up and they were mixing the dry-pack used to float the floor. We’re moving right along.

House rules prohibit construction on Sunday. I guess that’s so we have a whole day not masking the noise of that goddamn fountain with something like the sound of someone rolling on water-proofing. Anyway, we’ll continue on Monday. It won’t be long ’til I’m sharing my sleeping quarters with a wet saw.

I bought a few protea and tropicals at the swap meet. Now I need Laurel here to figure out what to do with them. I guess we’ll have to settle for “Boy arranging.”

Paul’s helper is a bit camera shy so the live cam will be turned into Lanai Cam for the day.

[nggallery id=6]

Early morning astronomics

Up early for an ISS pass and this month’s last setting of the moon in a waxing gibbous phase (just before it’s full). It’s always my favorite moonset because the sky is still quite dark, but the disk is almost full.  ISS pass was at 5:05 and well before sunrise, so the period of visibility was quite short–so short, I that missed it. The clouds cooperated, so I did get to track the moon until it disapeared behind Lanai. Beautiful way to start the day.

[singlepic id=18 w=600 h=900 float=]

[singlepic id=19 w=600 h=450 float=]

Live Camera

Live camera, such as it is, is up. It can be accessed via the main menu bar.

Keep in mind, images are only updated during working hours and it’s a really crappy cam, so the pictures won’t be wonderful. I will say, that old cam did survive the mayhem of that was the kitchen remod.

35 mm shots will be posted as I get time.

Plumbing rough-in is pau!

Water’s back on, plumber is packing up, nothing seems to be dripping. Time for lunch.

Today, there was tension in places other than the cables running through the pre-stressed concrete floors of Hale Kihei. It’s important to point out that this had nothing to do with the quality of work or the job the plumber was doing; it’s just that I’m a serious worry-wort when it comes to this kind of stuff in the condo. First there was the noise. To remove the tub, it had to be cut into pieces with a Sawz-all and edge grinder and making cuts it a porcelain-coated steel tub was, I think, the noisiest thing I’ve ever heard at Kamaole Sands. Once the tub was gone there was a good half hour of impact racket. The plaster of Paris around the old drain had to be chipped out and some of the concrete at the edge of the opening needed a little “dressing” with a jack hammer.

If the racket wasn’t enough, at one point in time there was considerable doubt about being able to fit a shower P trap in the hole that had been occupied by the old bath drain. In poured concrete structures laced with steel cables, you frequently wind up in situations where you don’t have a lot of options and if we couldn’t make room for the trap, our choices were pretty much limited to installing a new tub or filling the old tub space with a pinball machine and doing away with all bathing facilities in that WC. Neither of those choices seemed appealing.

My third trip around the worry beads came from a five gallon bucket the plumber had used to drain the pipes. At one point in time, it was suspended from the old valve set and I could just see it falling off, tipping over and dumping 3+ gallons of water through the newly-opened hole in the floor that leads to the ceiling of the shower of our neighbors below. Plumber completed his tasks without spilling a drop, the new fixtures are water tight and I need a beer.